TENDERING, ESTIMATING AND QUANTITY SURVEYING – Tendering Methods & procedures
TENDERING,
ESTIMATING AND QUANTITY SURVEYING – Tendering Methods & procedures:
Tendering Methods
& procedures:
Methods of Contractor
Selection:
The selection of a
contractor to carry out construction works in a project is a very important
matter.
A wrong choice may
lead to an unhappy client / contractor relationship.
It also may end up
with dissatisfied client and sometimes even with an insolvent contractor.
The client’s
professional advisers should find a contracting company;
That is financially
stable / and has a good business record.
For which the size of
project is neither too small nor too large.
That has a reputation
for good quality workmanship and efficient organization.
There are three
principal methods for choosing a contractor:
(a) open tendering,
(b) selective
tendering,
(c) nomination.
Open Tendering –
Initiated by client’s
architect/ quantity surveyor advertising in newspapers and/or inviting
contractors to apply for tender documents and to tender in
competition for
carrying out the work. Usually a deposit is required to discourage
irresponsible applicants, the deposit being returnable on the submission
of the tender.
Advantages –
There can be no
favoritism.
Can get the maximum
benefit from competition.
An opportunity is
provided for any capable firm.
Disadvantages –
There is a danger that
a firm inexperienced in preparing tenders may submit the lowest tender.
There is no guarantee
that the lowest tenderer is sufficiently capable or financially stable.
Total cost of
tendering is increased.
Selective Tendering –
A short list drawn up
of contractors who are considered to be suitable to carry out the proposed
work.
Names may be selected
from an approved list or ‘panel’ maintained by the client.
It is recommended that
the number of tenderers should be limited to between five and eight, depending
on the size of the contract.
If the firms on the
list are all reputable, well established and suitable for the proposed work,
then the selection is resolved into a question of price only.
Advantages –
Ensures that only
capable and approved firms submit tenders.
Reduce the cost of
tendering.
Disadvantages –
Cost level of the
tenders will be higher due to less competition and also due to the higher
caliber of the tenderers.
Nomination –
Sometimes referred as
‘single tendering’.
It is a special case
of selective tendering where the short list has only one name.
Used when the client
has a preference for a particular firm, often because it has done satisfactory
works for him before.
Competition is
eliminated and that will lead to a higher price.
Contract sum will be
arrived by a process of negotiations.
When a large project
is to be carried out in successive phases, a combination of selective tendering
and nomination is employed –
this is sometimes
called “serial tendering”.
*The contractor is
chosen for the first phase by means of selective competitive tendering.
*The accepted tender
forms the basis of payment for the resulting contract.
*The tender is also
used for the second and later phases, provision being made for so doing in the
initial contract by the inclusion of a
formula for updating
prices.
The purpose of serial
tendering is to gain the benefits of continuity.
*The contractor for
the first phase of the project will have his site organization set up, his
offices and storage huts, etc., already in
use and plant of
various kinds on the site.
*When the second phase
commences, these facilities will be already available.
It allows smooth
transition with less additional expenses.
*In addition, the
contractor’s workforce will be familiar with the details of the construction
after building the first phase, and it helps to
work more speedily and
efficiently.
Negotiated Contracts:
1.
This may be done using bills of quantities / schedules of rates.
2.
The rates and prices are discussed and agreed until eventually a
total price is arrived.
3.
Usually negotiation will be conducted between the contractor’s
quantity surveyor and the project quantity surveyor.
4.
One party will usually price the tender document first of all,
then the other party go through the rates and prices ticking off those which
are acceptable.
5.
When agreement is reached, a contract will be entered between
the client and the contractor.
6.
This process is sometimes called Single stage
negotiation.
In this procedure,
absence of competition usually results in a higher price.
Therefore, with a view
to gaining the benefits of competition as well as the advantages of
negotiation, a process of limited competition for the
selection of
contractor, followed by negotiation with him on the details of his tender, is
used.
This process is
usually known as two-stage negotiation.
In the first stage
tenderers are informed of the second stage intention and are asked to tender on
the basis of
Schedule of rates
consisting of the main/ significant items only.
Prices for the main
preliminary items;
Construction program
showing estimated times.
Labor and plant
resources/ construction methods.
Details of all labor
rates / material prices / discounts, etc.
Discussion with each
of the tenderers may be conducted in order to clarify their proposals.
Having selected a
contractor at the end of the competition stage, negotiation will follow on the
basis of a detailed tender document as in
single stage
negotiation.
Two-stage negotiation
is the method normally used to select a contractor to carry out management contract,
in which the general contractor
does little or none of
the construction work himself but organizes sub contractors to do the work.
Tender Document:
The number and nature
of tender documents will vary with the type of contract.
They will include some
or all of the following;
Conditions of
Contract:
This document sets out
the obligations and rights of the parties.
1.
Bills of Quantities.
2.
Specifications.
3.
Drawings:
Normally general
arrangement drawings will be provided.
Tenderers are not
normally given working drawings.
Full descriptions of
the work are incorporated in the bills or specifications.
Tenderers are informed
that they can inspect drawings not supplied to them at the architect’s office.
Form of Tender:
This is a pre-printed
formal statement, often in the form of a letter, in which tenderer fills in, in
the blank spaces, his name and address and the sum
of money for which he
offers to carry out the work shown on the drawings and described in the bills
of quantities or specifications.
Return Envelope:
Each tenderer should
be supplied with a pre-addressed envelope clearly marked “Tender for -
name of the project”.
This will ensure that
tenders are recognized as such when received and will not be accidentally
opened.
Tenderers should be
asked to acknowledge in writing receipt of the tender document.
Tendering Procedure:
Preliminary Enquiry:
It is recommended
practice (not always followed) to send, about a month beforehand, to each of
the firms from whom it is proposed to invite a tender, a
preliminary inquiry,
to ascertain that they are willing to submit a tender.
This avoids the
situation of contractors declining to tender, or if they prefer not to decline,
submitting a ‘cover price’, i.e. a price which is high enough to
be well above the
lowest tender.
Sufficient information
about the project should be given in the preliminary enquiry letter to enable
each contractor to decide whether he is in a position to
meet the
terms.
Period for Preparation
of Tenders:
It is important that
tenderers are given sufficient time to make all necessary enquiries from
suppliers, sub-traders, etc. and the date for return of tenders
should be fixed so as
to allow for the amount of work likely to be involved in preparing tender.
Four weeks is
recommended as a minimum period, although it is possible, in exceptional cases,
for less time to be adequate.
A time of the day
should be specified as the latest time for tenders to be received on the date
fixed.
Any tenders arriving
later should be returned.
Parity of Tendering:
It is important that
all tenders should be based on the same information.
All the tender
documents must be identical.
A tenderer may
telephone the architect / project quantity surveyor about an item in the bills
of quantities or a clause in the specification. He may question
the accuracy of a
quantity or unavailability of a specified material in the market.
Such queries must be
answered and must be dealt with promptly.
But, whatever the
reply given to the enquirer must be communicated to all other tenderers,
immediately by telephone and then confirmed in writing.
The same procedure
must be followed if an error is discovered or if it is decided to extend the
time for the receipt of tenders.
The tenderer should be
asked to confirm in writing the receipt of every written communication of
additional or varied information.
Opening of Tenders:
A formal procedure
should be followed for opening tenders to eliminate any suspicion or
irregularities.
No tender must be
opened before the latest time for submission.
As little time as
reasonably possible should be allowed to elapse before opening tenders and they
should all be opened at the same time.
Notifying the
Tenderers:
As soon as possible
after opening of tenders, all tenderers should be informed, then each tenderer
will know whether his tender is successful or not
and be able to judge
his future commitments.
This is a duty of
often falls to the project quantity surveyor.
No comments
Post a Comment