Estimating and Tendering for Construction Work, 3rd Edition
Estimating and Tendering for Construction Work, 3rd Edition
Contents
Preface ix
Acknowledgements xii
List of figures xiii
Abbreviations used in the text xvi
1 Organization of the estimating function 1
2 Procurement paths 10
Introduction 10
Clients’ needs 11
Contractor involvement 12
Partnering 13
Apportionment of risk 14
Traditional method 16
Design and build 17
Management contracting 19
Construction management 21
Private finance initiative 22
3 Forms of contract 34
Introduction 34
Essentials of a valid construction contract 34
Standard forms of contract 36
Sub-contract forms 38
Comparison of forms 43
Selection of contract forms 44
4 Tender documentation 46
Introduction 46
Coordinated project information 47
CPI and the estimator 55
Documents used as the basis of a tender 58
Formal tender documents 61
v5 Estimating methods 66
Introduction 66
Single-rate approximate estimating 70
Multiple-rate approximate estimating 71
Approximate quantities 73
Analytical estimating 78
Operational estimating 82
6 Contractor selection and decision to tender 85
Introduction 85
Competition and negotiation 86
Abuse of tendering procedures 90
Decision to tender 92
Inspection of tender documents 95
Competition legislation 96
7 Project appreciation 100
Introduction 100
Estimate timetable 100
Pricing strategy 103
Schedules 103
The estimating team 103
Visits to consultants and site 107
8 Enquiries to suppliers and sub-contractors 109
Introduction 109
Enquiries for materials 111
Enquiries to sub-contractors 113
9 Tender planning and method statements 117
Introduction 117
The role of the planning engineer 117
Method statements 118
Tender programmes 119
10 Resource costs – labour, materials and plant 125
Introduction 125
Labour rates 125
Material rates 128
Plant rates 130
11 Unit rate pricing 132
Introduction 132
Contents
viComponents of a rate 132
Method of measurement 134
Pricing notes 134
Model rate and pricing examples 135
12 Sub-contractors and nominated suppliers 176
Introduction 176
Domestic sub-contractors 176
Nominated sub-contractors 183
Nominated suppliers 184
13 Fluctuations 185
Introduction 185
Standard fluctuations clauses 186
Calculation of non-recoverable increases 188
14 Provisional sums and dayworks 192
Introduction 192
Provisional sums for undefined work 192
Provisional sums for defined work 192
Dayworks 193
Overheads and profit 196
15 Project overheads 199
Introduction 199
Pricing project overheads 199
Pricing the preliminaries bill 202
Example of project overheads 216
16 Cashflow forecasts 217
Introduction 217
Cashflow calculations 217
Example of a contractor’s cashflow forecast 219
17 Completing the estimate and final tender review 227
Completing the estimate 227
Estimator’s report 229
Comments on Estimate Analysis form 229
Comments on Tender Summary form 234
Risks and opportunities 235
Overheads and profit 237
18 Tender submission and results 240
Introduction 240
Contents
viiCompletion of priced bills 241
Tender presentation 243
Vetting of tenders 245
Post-tender negotiations and award 246
Tendering performance and analysis of results 247
Bidding strategy 251
19 Action with the successful tender 254
Introduction 254
Information transfer 254
Feedback 256
20 Computer-aided estimating 260
Introduction 260
Aims of computer-aided estimating 261
Software 262
Electronic exchange of information 263
Reverse auctions 265
Computer-aided estimating packages 267
General purpose software 271
Hardware 280
Networking 283
Implementation 285
The future 286
Further reading 291
Index 295
Contents
No comments
Post a Comment