Rate Analysis for centering & shuttering

Rate Analysis for centering & shuttering
Sl. No.
Description
Unit
Qty.
Rate
(in Rs.)
Amount
(in Rs.)
1
Centering & shuttering with plywood or steel sheets including strutting, propping, bracing bothways with wooden members and removal of formwork upto 4.50 mtr. Height above ground level, for suspended floors, roofs, landings, staircase, balconies, girders, cantilevers, bands, copings, bed plates, anchor blocks, sills chajjas, etc.













Unit = Sq.m.





Taking output = 1 Sq.m




A
Material





Steel Plate 3.15 mm thick @ 24.73 kg/m2
kg
113.86
60.00
6831.60

(2.88x24.73) = 71.22 kg

Supporting Angle (35x35x5) @ 2.6 kg/m

(16.4x2.6) = 42.64 kg

Total Weight = 113.86 kg

(including welding, nuts & bolts ect.)

Add for maintenance @ 10 %



683.16

Cost of Supporting Material





Ballies 100 mm,75mm 3m long
No
5
60.00
300.00

Total



7814.76

Less salvage value after full use of material @ 20 % on A



-1562.95

Total - Part A



6251.81

Assuming shuttering of material will become unservicable after use of 40 times





Cost for using once
Once
1/40

156.30

Carriage
LS


15.00






B
Labour





Fitter
Nos
0.75
150.00
112.50

Beldar
Nos
1.5
80.00
120.00

Shuttering oil
LS


5.00





408.80

Add Overhead & Contractor's Profit 10 %



40.88

Total



449.67

Cost per Sqm



104.21




Say
104.00