Rate Analysis for centering & shuttering
Rate Analysis for centering & shuttering
|
|||||
Sl.
No.
|
Description
|
Unit
|
Qty.
|
Rate
(in Rs.) |
Amount
(in Rs.) |
1
|
Centering & shuttering with
plywood or steel sheets including strutting, propping, bracing bothways with
wooden members and removal of formwork upto 4.50 mtr. Height above ground
level, for suspended floors, roofs, landings, staircase, balconies, girders,
cantilevers, bands, copings, bed plates, anchor blocks, sills chajjas, etc.
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Unit =
Sq.m.
|
|
|
|
|
|
Taking
output = 1 Sq.m
|
|
|
|
|
A
|
Material
|
|
|
|
|
|
Steel Plate 3.15 mm thick @ 24.73
kg/m2
|
kg
|
113.86
|
60.00
|
6831.60
|
|
(2.88x24.73) = 71.22 kg
|
||||
|
Supporting Angle (35x35x5) @ 2.6
kg/m
|
||||
|
(16.4x2.6) = 42.64 kg
|
||||
|
Total Weight = 113.86 kg
|
||||
|
(including welding, nuts &
bolts ect.)
|
||||
|
Add for maintenance @ 10 %
|
|
|
|
683.16
|
|
Cost of Supporting Material
|
|
|
|
|
|
Ballies 100 mm,75mm 3m long
|
No
|
5
|
60.00
|
300.00
|
|
Total
|
|
|
|
7814.76
|
|
Less salvage value after full use
of material @ 20 % on A
|
|
|
|
-1562.95
|
|
Total
- Part A
|
|
|
|
6251.81
|
|
Assuming shuttering of material
will become unservicable after use of 40 times
|
|
|
|
|
|
Cost for using once
|
Once
|
1/40
|
|
156.30
|
|
Carriage
|
LS
|
|
|
15.00
|
|
|
|
|
|
|
B
|
Labour
|
|
|
|
|
|
Fitter
|
Nos
|
0.75
|
150.00
|
112.50
|
|
Beldar
|
Nos
|
1.5
|
80.00
|
120.00
|
|
Shuttering oil
|
LS
|
|
|
5.00
|
|
|
|
|
|
408.80
|
|
Add Overhead & Contractor's
Profit 10 %
|
|
|
|
40.88
|
|
Total
|
|
|
|
449.67
|
|
Cost per Sqm
|
|
|
|
104.21
|
|
|
|
|
Say
|
104.00
|