Labour Work Per Day work detail
Particulars of items
|
Quantity
|
Perday
|
|
1.
|
Brick
work in lime or cement mortar in foundation and plinth
|
1.25cum
|
(45cuft)per
mason
|
2.
|
Brick
work in lime or cement mortar in superstructure
|
1.00cum
|
(35cuft)per
mason
|
3.
|
Brick
work in mud mortar in foundation and plinth
|
1.50cum
|
(55cuft)per
mason
|
4.
|
Brick
work in mud mortar in superstructure
|
1.25cum
|
(45cuft)per
mason
|
5.
|
Brick
in cement or lime mortar in arches
|
0.55
cum
|
(20cuft)per
mason
|
6.
|
Brick
in cement or lime mortar in jack arches
|
0.55
cum
|
(20cuft)per
mason
|
7.
|
Half
brick wall in partition
|
5.00sqm
|
(50sqft)per
mason
|
8.
|
Coursed
rubble stone masonry in lime cement mortar including dressing
|
0.80cum
|
(30
cuft)per mason
|
9.
|
Random
rubble stone masonry in lime or cement mortar
|
1.00cum
|
(35cuft)per
mason
|
10.
|
Ashlars
masonry in lime or cement mortar
|
0.40cum
|
(15cuft)per
mason
|
11.
|
Stone
arch work
|
0.40cum
|
(15cuft)per
mason
|
12.
|
Lime
concrete in foundation or floor
|
8.50cum
|
(300cuft)per
mason
|
13.
|
Lime
concrete in roof terracing
|
6.00cum
|
(200cuft)per
mason
|
14.
|
Lime
concrete 1:2;4
|
5.00cum
|
(175cuft)per
mason
|
15.
|
RB
work
|
1.00cum
|
(35cuft)per
mason
|
16.
|
RCC
work
|
3.00cum
|
(125cuft)per
mason
|
17.
|
12mm
(1/2) plastering with cement or lime mortar
|
8.00sqm
|
(80sqft)per
mason
|
18.
|
Pointing
with cement or lime mortar
|
10.00sqm
|
(100sqft)per
mason
|
19.
|
White
washing or colour washing coats
|
70.00sqm
|
(700sqft)per
white washer
|
20.
|
White
washing or colour washing coats
|
200.00sqm
|
(2000sqft)per
white washer
|
21.
|
Painting
or varnishing doors or windows one coat
|
25sqm
|
(250sqft)per
painter
|
22.
|
Coal
tarring or soligum painting one coat
|
35.00sqm
|
(350sqft)per
painter
|
23.
|
Painting
large surface one coat
|
35.00sqm
|
(350sqft)per
painter
|
24.
|
Distempering
one coat
|
35.00sqm
|
(350sqft)per
painter
|
25.
|
2.5cm(1’)
CC floor
|
7.50sqm
|
(75sqft)per
painter
|
26.
|
Flag
store floor laying with lime or cement mortar excluding LC
|
10.00sqm
|
(100sqft)per
painter
|
27.
|
Brick
on edge in floor lime or cement mortar excluding LC
|
7.00sqm
|
(70sqft)per
painter
|
28.
|
Brick
bat floor as in above
|
8.00sqm
|
(80sqft)per
painter
|
29.
|
Timber
framing sal or teak wood
|
0.07cum
|
(2.5cuft)percarpenter
|
30.
|
Timber
framing sal or country wood
|
0.15cum
|
(5cuft)per
carpenter
|
31.
|
Door
and window shutters paneled or glazed
|
0.15sqm
|
(7sqft)
per carpenter
|
|
|
|
|
32.
|
Door
and window shutters paneled or battened
|
0.80sqm
|
(0.80sqft)percarpenter
|
33.
|
Sawing
hard wood
|
4.00sqm
|
(40sqft)
per pair of sawers
|
34.
|
Sawing
soft wood
|
6.00sqm
|
(60sqft)
per pair of sawers
|
35.
|
Single allahabad tiling or mangalore
tiling
|
6.00sqm
|
(60sqft)
per tile layer
|
36.
|
Double allahabad tiling
|
4.00sqm
|
(40sqft)
per tile layer
|
37.
|
Breaking
of brick ballest 40mm (11/2”) gauge
|
0.75cum
|
(35cuft)per
labourer or breaker
|
38.
|
Breaking
of brick ballest 25mm (1”) gauge
|
0.55cum
|
(20cuft)per
labourer or breaker
|
39.
|
Breaking
of stone ballest 40mm (11/2”) gauge
|
0.40cum
|
(10cuft)per
labourer or breaker
|
40.
|
Breaking
of stone ballest 25mm (1”) gauge
|
0.25cum
|
(10cuft)per
labourer or breaker
|
41.
|
Ashlar
stone dressing
|
0.70cum
|
(25cuft)perstonecutter
|
42.
|
Flag
stone dressing
|
1.50sqm
|
(25sqft)perstonecutter
|
43.
|
Earthwork
in excavation in ordinary soil
|
3.00cum
|
(100cuft)per
belder mazdoor
|
44.
|
Earthwork
in excavation in hard soil
|
2.00cum
|
(75cuft)per
belder mazdoor
|
45.
|
Excavation
in soil
|
1.00cum
|
(35cuft)per
belder mazdoor
|
46.
|
Number
of bricks laid by a mason in brick work upto a height of 3m(10”)
|
600
bricks per mason
|
|
47.
|
Amount
of work done by a mazdoor helper per day
|
|
|
|
Mix
|
3.00cum
|
(100cuft)mortar
per mazdoor
|
|
Deliver
brick
|
4000
nos to a distance of 15m (50”) per mazdoor
|
|
|
Deliver
mortar
|
5.5cum
|
(200cuft)
per mazdoor
|
48.
|
Scaffolding
cost for single storey building
|
Re.0.50per
cum
|
(Rest.1.5%cuft)
of brick work.
|
Items 46,47 and 48 are based on the committee report on rates and
cost government of India.
LABOUR (MAZDOOR)
REQUIRED FOR DIFFERENT WORKS
Extracts from the report on productivity
projects in building industries issued by National Building Organisation are
given below:-
a) Earthwork per
28.30 cum (12000cuft)
1) Excavation in
foundations, trenches etc., in ordinary soil including disposal up to 30m
(100’) and lift of 1.5m(5ft) –5 beldars and 4 mazdoors can do 28.30 cum
(1000cuft) per day.
2) Refilling excavated
earth in foundations, pointh etc, including consolidation in 15cm(6”) layers-3
beldars, 2 mazdoors and ½ bhisti can do 28.30 cum (1000cuft) per day.
3) Disposal of surplus
earth within a lead of 30m (100’)-1 mazdoor can do 2.83cum (100 cuft) per day.
b) Cement concrete
work per 2.83 cum (100cuft)
laying cement concrete – 2 beldars, 3 mazdoors, ¾ bhisti and
¼ mason, can do 2.83 cum (100 cuft) per day.
c) R C C work:-
1) Laying reinforced concrete – 3 beldars, 3 mazdoors, 1½
Bhisti and ½ mason can do 2.83 cum (100cuft) per day.
2) Centering and shuttering for flat surfaces – 4 beldars and
4 carpenters (II class) can do 9.6sqm(96sqft) per day.
3)Reinforcement work for R C C –1 blacksmith or fitter and 1
beldar can bend and place in position 1 quintal (2 cwt) of steel per day.
d) Stone work per
2.83 cum (100cuft)-
Random rubble masonry with blue stone in foundations-3
masons, 3 beldars, 2 mazdoors and 1/4bhisti can do 2.83 cum (100cuft0 per day
e) Brick work per 2.83
cum (100cuft)-
First class brick work in 1:4 cement mortar in superstructure
partition walls, junctions of roof, parapet walls and string course –
2½masons,4½ mazdoors
and 1/2 bhisti can do 2.83 cum (100cuft) per day.
F) Wood work :-
1) For the frames of
doors and windows –2 carpenters and 1 beldar can work 0.18 cum (6.40cuft) of
wood equivalent to door frames 7.5cm x 10m of 1.2m x 2.1m (3’x4’of
3’x11’x7’)size per day.
2) For paneled, glazed,
etc, shutters-15 carpenters and 4 beldars can make and fix 4 shutters 40 mm
thick of size 2.00m x 1.15m (1 ½ thick of size of 6’-9x 3’-9’) per day. Quantity of wood per
shutter – 0.075 cum, ie2.66 cuft.
g) Iron work :-
1) Fixing 40mm x
3mm=38cm(1 ½ “ x ½ ‘x 15”0 flat iron holdfasts-1 blacksmith (II class), I mason
and I beldar can fix 36 holdfasts per day.
2) Fixing 16mm dia. 5/3”
dia) M S rods –1 blacksmith (II class), 2 carpenters (II class) and 3 mazdoors
can fix 16.5m (54rft) per day.
h) Flooring: -
4cm thick (1 1/2 “)thick cement concrete flooring of 40sqm
(400sqft) require 5 masons, 4 beldars, 3 mazdoors and 1 bhisti per day for
mixing laying and finishing.
I) Finishing :-
1) Plastering
with any mortar 12mm (5”) thick – 3 masons, 3 mazdoors and 1 bhisti can plaster
40sqm (400a ft)
per day.
2)White washing or colour washing (3 coats) – 1 white washer
and 1 mazdoor can do 60sqm (600sqft) per day.
3) Painting two coats
such as chocolate, red, grey, etc on wood are steel –3
Painters and 2 mazdoors can paint 10sqm (100sqft) per day.
LOAD FOR A TWO
–BULLOCKS CART
|
|
Quantity
or Number
|
|
Sl#
|
Particulars of materials
|
On Kachcha Road
|
On Pucca Road
|
|
Brick 19 cm x
9cm x 9cm
|
275nos
|
400nos
|
|
Brick ballast
|
0.85 cum
(30cuft)
|
1.10 cum
(40cuft)
|
|
Stone ballast
|
0.70 cum (25
cuft)
|
1.00 cum
(35cuft)
|
|
Kankar
|
0.85 cum
(30cuft)
|
1.10 cum
(40cuft)
|
|
Sand surkhi
|
0.85 cum
(30cuft)
|
1.10 cum
(40cuft)
|
|
Lime
|
1.10 cum
(40cuft)
|
1.40 cum
(50cuft)
|
|
Tiles Allahabad or Mangalore
|
275nos
|
400nos
|
|
Cement
|
15bags
|
20 bags
|
|
Steel
|
0.75 tonne
|
1 tonne
|
Note; A bullock
……..carry about one tonne load. The average speed for
a bullock cart may be taken as 3.20km (2 units) per hour and ¾ hour may be
allowed for loading and unloading. Taking 8 hours
working per day, the number of trips per day, can be calculated.
LOAD FOR TRUCKS
ON PUCCA METALLED
ROAD –
Trucks3 tonners 5 tonners8 tonners
diesel truck
Brick
or Allahbad tiles or
Mangalore
tiles1000nos 1500nos2000nos
Cement, steel and
other
Heavy materials 3 tonne 5 tonne8 tonne
Other materials –
Ballast, Kankar, grit
Sand coal, etc., 2.8cum 4.20cum5.6cum
(100cuft) (150cuft)(200cuft)
On kachcha earthen
road the load will be less by 33 per cent.
MATERIALS FOR DIFFERENT
ITEMS OF WORKS
The requirement of
materials for different items of works is as given below:-
Sl#
|
Particulars
|
Quantity
|
|
1.
|
Bricks (9” x
4 ½ “ x3” or 20 cm x 10cm x 10cm nominal size) for brick work
|
1350 nos for
100cuft
|
50000 nos per
% cum (500nos.per cum)
|
2.
|
Dry mortar
for brick work 30%
|
30cuft for
100 cuft
|
30cum for 100
cum
|
3.
|
Stone for
rubble stone masonry 125%
|
125cuft for
100 cuft
|
125cum for
100 cum
|
4.
|
Dry mortar
for rubble stone masonry 42%
|
42cuft for
100 cuft
|
42cum for 100
cum
|
5.
|
Bricks for
brick ballast for lime concrete
|
1050cuft for
100 cuft
|
37000cum for
100 cum
|
6.
|
Brick bats or
brick ballast for lime concrete
|
150cuft for
100 cuft
|
150cum for
100 cum
|
7.
|
Brick ballast
for lime concrete
|
100cuft for
100 cuft
|
100cum for
100 cum
|
|
|
|
|
Sl#
|
Particulars
|
Quantity
|
|
8.
|
Dry mortar
for lime concrete I foundation and floor 35%
|
35cuft for
100cuft
|
35cum for 100
cum
|
9.
|
Dry mortar
for lime concrete in roof terracing 45%
|
45cuft for
100cuft
|
45cum for 100
cum
|
10.
|
Materials for
cement concrete 1:2:4
|
|
|
|
Ballast or
grit 88%
|
88cuft for
100cuft
|
88cum for 100
cum
|
|
Sand 44%
|
44cuft for
100cuft
|
44cum for 100
cum
|
|
Cement 22%
|
22cuft for
100cuft
|
22cum (60
bags)for 100 cum
|
11.
|
Materials for
2.5cm (1”)cc 1:2:4 floor
|
|
|
|
Stone grit
|
8cuft for
100sqft
|
2.40cum for
100 cum
|
|
Sand
|
4cuft for
100sqft
|
1.20cum for
100 cum
|
|
Cement
|
2 ¼cuft (2
bags) for 100cuft
|
0.08cum (24
bags)for 100 cum
|
12.
|
Bricks for R
B work
|
1200 nos for
100cuft
|
42000nos/% cum(420 mps.[er ci,)
|
13.
|
Dry mortar
for R B work 45%
|
45cuft for
100cuft
|
45cum for 100
cum
|
14.
|
Dry mortar
for 12mm (1/2) plastering
|
6cuft for
100sqft
|
2.00cum for
100 sqm
|
15.
|
Dry mortar
for pointing in brickwork
|
2cuft for
100sqft
|
0.60cum for
100 sqm
|
16.
|
Lime for
white washing one coat
|
1kg for
100sqft
|
10kg for 100
sqm
|
17.
|
Dry distemper
for ist coat
|
0.65 kg for
100sqft
|
6 ½ kg for
100 sqm
|
18.
|
Dry distemper
for 2nd coat
|
0.50 kg for
100sqft
|
5kg for 100
sqm
|
19.
|
Snow-Cem for
Ist coat
|
3kg for
100sqft
|
30kg for 100
sqm
|
20.
|
Snow-Cem for
2nd coat
|
2kg for
100sqft
|
20kg for 100
sqm
|
21.
|
Paint ready
mixed for painting one coat
|
1/3gl.for
100sqft
|
10ltr for 100
sqm
|
22.
|
Paint (stiff)
for painting one coat
|
1kg for
100sqft
|
10kg for 100
sqm
|
23.
|
Bricks (20 x
10 x 10cm) for brick floor or half brick wall
|
500 nos for
100sqft
|
5000nos.for
100sqm
|
24.
|
Dry mortar
for brick floor or half brick wall
|
12cuft for
100sqft
|
3.20 cum for
100 sqm
|
25.
|
Bricks (9” x
4 ½ “ x3”) for brick flat work
|
350 nos for
100sqft
|
3500nos.for
100sqm
|
26.
|
Dry mortar
for brick flat floor
|
8cuft for
100sqft
|
2.25cum for
100 cum
|
27.
|
Bricks (9” x
4 ½ “ x3”) required for honey comb wall
|
325 nos for
100sqft
|
3250 nos.for
100sqm
|
28.
|
Dry mortar
for honey comb wall
|
8cuft for
100sqft
|
2.5cum for
100 cum
|
29.
|
Materials for
2cm (3/4”)thick damp proof course of 1:2 cement mortar
|
|
|
|
Cement
|
3cuft
(2.5bags) for 100sqft
|
0.90cum (27
bags)for 100 cum
|
|
Sand
|
6cuft for
100sqft
|
1.80cum for
100 cum
|
|
Compound or
impermo @ 1kg per bag of cement
|
2.5kg for 100sqft
|
27kg for 100
sqm
|
30.
|
Materials for
2.5cm (1”)cc 1:1 ½ :3 damp proof course
|
|
|
|
Stone grit
|
8cuft for
100sqft
|
2.25cum for
100 cum
|
|
Sand coarse
|
4cuft for
100sqft
|
1.13cum for
100 cum
|
|
Cement
|
2 ½ cuft (2 ½
bags) for 100sqft
|
0.75cum for
(221/2bags)for100 cum
|
|
Compound or
impermo @ 1kg per bag of cement
|
21/2 kg for
100sqft
|
22½ kg for 100 sqm
|
31.
|
Bitumen or
asphalt for painting on D P C or on roof – 1st coat
|
15 kg for
100sqft
|
150 kg for
100 sqm
|
|
2nd coat
|
10 kg for
100sqft
|
100 kg for
100 sqm
|
32.
|
G G I sheet
for roof
|
128sqft for
100sqft
|
128 sqmfor
100sqm
|
33.
|
A G
corrugated sheet for roof
|
115sqft for
100sqft
|
115 sqmfor
100sqm
|
34.
|
Timber for
paneled door shutter 4cm (1 ½”) thick
|
15cuft for
100sqft
|
4.5 cum for
100 cum
|
35.
|
Timber for
battend door shutter 4cm (1 ½”) thick
|
13cuft for
100sqft
|
4.0 cum for
100 cum
|
36.
|
Timber for
paneled & glazed shutter 4cm (1 ½”) thick
|
11cuft for
100sqft
|
3.0 cum for
100 cum
|
|
Timber for
fully glazed shutter 4cm (1 ½”) thick
|
8cuft for
100sqft
|
2.0 cum for
100 cum
|
No comments
Post a Comment