LABOUR ESTIMATE FOR VARIOUS ITEMS OF WORKS
LABOUR ESTIMATE FOR VARIOUS ITEMS OF
WORKS
|
|||
SN.
|
ITEM DESCRIPTION
|
QUANTITY
|
LABOUR ( 8 hours per day)
|
1.
|
Concrete
in Foundation.
|
10
m3
|
Head
Mason 1/4, Mason 2, Labour 20
|
2.
|
R.C.C.
M - 15 grade.
|
10
m3
|
Head
Mason 1/2, Mason 3, Labour 23
|
Note:
For each additional storey, the strength should be increased by 6 nos. for
volume of 10 cu.m to lift the materials.
|
|||
3.
|
Supplying,
fitting, fixing and removing shuttering & staging.
|
7
m2
|
Carpenter
1, Labour 2
|
4.
|
Reinforcement
for R.C.C. work including cutting, bending and placing in position.
|
100
kg.
|
Bar
binder (Black- smith/fitter) 1, Labour 1
|
5.
|
Damp
proof course.
|
100
m2
|
Head
Mason 1/2, Mason 5, Labour 6
|
6.
|
First
class brickwork in 1:6 in super structure.
|
10
m3
|
Head
Mason 1/2, Mason 9, Labour 18, Bhisti 2
|
7.
|
Brick
on edge flooring with cement Mortar (1:3).
|
100
m2
|
Head
Mason 1/2, Mason 10, Labour 14, Bhisti 1
|
8.
|
Ironite
flooring (40mm thk).
|
100
m2
|
Head
Mason 1, Mason 24, Labour 27, Labour for Scrubbing 3
|
9.
|
C.G.I
sheeting on roof
|
10
m2
|
Carpenter
1, Fitter (Blacksmith) 1/2, Labour 2
|
10.
|
C.I.
rain water pipe fixing.
|
9
m
|
Mason
1/2, Labour 2.5
|
11.
|
12mm
thk cement plaster on brickwork in 1:6.
|
100
m2
|
Head
Mason 1, Mason 10, Labour 14, Bhisti 1
|
12.
|
Ruled
pointing (1:3).
|
100
m2
|
Head
mason 1/2, Mason 10, Labour 9, Bhisti 1
|
13.
|
White
washing primer coat and 2 finished coats to new plaster.
|
100
m2
|
Painter
1/2, Labour 2
|
14.
|
Dry
Distemper
|
100
m2
|
Painter
8.5, Labour 5.5
|
15.
|
Plastic
Emulsion paint on new work.
|
100
m2
|
Painter
5.5, Labour (Helper) 5.5
|
16.
|
Primer
coat on wood work/ steel work.
|
100
m2
|
Painter
2.5, Labour (Helper) 2.5
|
17.
|
Panting
two coats over priming coat for new wood work/steel work.
|
100
m2
|
Painter
5.5, Labour (Helper) 5.5
|
18.
|
Demolishing
cement concrete (1:2:4/1:3:6) including lead upto 50m.
|
10
m3
|
Labour 23
|
19.
|
Demolishing
R.C.C. work including lead upto 50m.
|
10
m3
|
Labour 33.5
|
20.
|
Demolishing
Brickwork in cement mortar including stacking of serviceable material and
disposal of unserviceable materials within a lead of 50m.
|
10
m3
|
Labour 19.5
|
21.
|
Removing
mortar and cleaning bricks and stacking cleaned bricks.
|
10
m3
|
Mason
6, Labour 25
|
22.
|
Dismantling
doors & windows including framing, stacking of material.
|
1
no.
|
Mason
1, Labour 0.20
|
23.
|
Supplying
and fixing 12mn/15mm dia G.I. pipe with G.I. fittings and M.S. clamps
including cutting holes in walls and making good the same
|
100
r.m.
|
Fitter
7, Labour (Beldar) 6
|
24.
|
Supplying,
fitting and laying 25mm G.I pipes with G.I. fittings including trenching and
refilling of external work
|
100
r.m.
|
Fitter
1, Labour 8
|
25.
|
Laying,
fitting and fixing 100 mm dia G.I. pipes including testing of joint, trench
cutting for pipe laying upto a depth of 90 cm. and refilling, dressing etc.
|
20
r.m.
|
Fitter
1.5, Labour 13
|
26.
|
Supplying,
laying, joining 100 dia stoneware pipes with cement mortar 1:1 (excluding
earthwork etc.).
|
15
r.m..
|
Mason
1, Labour 2
|
27.
|
Wash
Basin with C.I. brackets, brass taps, brass plug with brass chain, waste pipe
Including cutting walls and making good the same.
|
1
no.
|
Plumber
1, Mason 1/2, Labour 1
|
28.
|
Sink.
|
1
no.
|
Plumber
1/2, Mason 1/2, Labour 1
|
29.
|
9"
thick brick flat soling filled with local sand.
|
10
m2
|
Labour 1
|
30.
|
Earth
work for roads including cutting, loading, unloading, carrying &
dressing.
|
10
m2
|
Labour 4
|
31.
|
Stone
soling for roads including packing with smaller stones manually.
|
10
m3
|
Labour 7
|
32.
|
Stone
soling for roads including packing with smaller stones With steam roller.
|
20
m3
|
Labour 7
|
33.
|
Surface
dressing/Bituminous carpeting on roads
|
100
m2
|
Labour (for one layer) 10,
Labour (for two layers) 15
|
No comments
Post a Comment