General Notes for civil Engineering
General Notes for civil Engineering
Electrical conduits shall not run in column
Earth work excavation for basement above 3 m
Should be stepped form
Any Back filling shall be compacted 95% of
dry density at the optimum moisture
content and in layers not more than 200mm for filling above structure and 300
mm for no structure
F SOLING IS SPECIFIED THE SOLING STONES
SHALL BE LAID AT 45° TO 60° INCLINATION
(AND NOT VERTICAL) WITH INTERSTICES
FILLED WITH SAND OR MOORUM.
Y REPRESENTS TOR STEEL GRADE - Fe-415 OF
IS:1786. WITH CHARECTERISTIC YIELD
STRENGTH OF 415 N/MM MINIMUM.
∅ REPRESENTS MILD STEEL GRADE - 1 OF IS:432
(PART-1)
ALL REINFORCEMENT SHALL BE FREE FROM MILL
SCALES, LOOSE RUST & COATS OF PAINTS, OIL OR ANY OTHER SUBSTANCES.
BY PROVIDING PROPER COVER BLOCKS, SPACERS,
CHAIRS ETC.. ALL REINFORCEMENT SHALL BE
PLACED AND MAINTAINED IN POSITION AS SHOWN IN STRUCTURAL DRAWING
CEMENT SHALL BE 43 GRADE ORDINARY PORTLAND
CEMENT CONFORMING TO IS:8112 OR53 GRADE
ORDINARY PORTLAND CEMENT CONFORMING TO
IS:12269-1987.
CEMENT SHALL BE STORED IN DRY PLACES ON A RAISED PLATFORM ABOUT 200mm ABOVE FLOOR LEVEL AND
300mm
AWAY
FROM WALLS. BAGS TO BE STACKED NOT MORE THAN
10 BAGS HIGH IN SUCH A MANNER THAT IT IS ADEQUATELY PROTECTED FROM MOISTURE AND CONTAMINATION.
WATER USED FOR BOTH MIXING AND CURING SHALL
BE CLEAN AND FREE FROM INJURIOUS AMOUNTS
OF OILS, ACIDS, ALKALIS, SALTS, SUGAR AND ORGANIC MATERIALS OR OTHER SUBSTANCES THAT MAY BE DELETERIOUS
TO CONCRETE OR STEEL. THE pH SHALL BE GENERALLY
BETWEEN 6 AND 8.
CEMENT SHALL BE TESTED FOR ITS
SETTING.
1. THE INITIAL SETTING TIME SHALL NOT BE LESS
THAN 30 MINUTES.
2. THE FINAL SETTING TIME SHALL NOT BE MORE THAN
10 HOURS.SAMPLES FROM FRESH CONCRETE SHALL BE TAKEN AND AT LEAST A SET OF 6
CUBES OF 150mm SHALL BE PREPARED AND CURED.
3. CUBES
EACH AT 7 DAYS AND 28 DAYS SHALL BE TESTED FOR COMPRESSIVE STRENGTH. THE TEST RESULTS SHOULD BE SUBMITTED TO ENGINEER FORAPPROVAL.
IF RESULTS ARE UNSATISFACTORY
NECESSARY ACTION/RECTIFICATION/REMEDIAL
MEASURES HAS TO BE EXERCISED.
A SET OF
CUBE TESTS SHALL BE CARRIED OUT FOR EACH 30 Cum OF CONCRETE / EACH LEVELS OF
CASTING / EACH BATCH OF CEMENT.
WATER
CEMENT RATIO FOR DIFFERENT GRADES OF CONCRETE
SHALL NOT EXCEED 0.45 FOR M20 AND ABOVE AND
0.50 FOR M10 / M15 CONTRACTOR / MIX DESIGNER TO
CARRY
OUT THE NECESSARY INITIAL (PRELIMINARY) TESTS.
FOR
CONCRETE GRADES M20 AND ABOVE APPROVED ADMIXTURE SHALL BE USED AS PER MIX
DESIGN REQUIREMENTS.